CarpentryIra Samuel Griffith

Opening the book…

Carpentry

Ira Samuel Griffith

ACKNOWLEDGMENTS

To my father, whose patient instruction and forbearing oversight during the period of carpentry apprenticeship has made possible the practical aspect of this present volume, grateful acknowledgment is made.

Acknowledgment is also made of assistance derived from the various trade magazines and from the few books on carpentry.

Credit is due Mr. franklin G. Elwood, Peoria, for most of the excellent drawings which accompany and clarify the text. A number of the drawings were penciled by Gordon Kellar, Boston. The photographs are the work of James F. Barham, Columbia, Mo-.

I. S. G.

PREFACE

I

IT is the author's hope that the following text may be of service to apprentices to the trade, to vocational and trade school students, and to manual training students. The author's experience as a carpenter leads him to feel that not a few journeyman carpenters may find their horizon widened and their usefulness as framers of the unusual roof increased by a study of Chapter IV where an effort has been made to indicate how the principles involved in framing the square and octagonal roof may be "generalized" so as to make possible their application to roofs of any number of sides. Beyond this, the book makes claims to being nothing more than an elementary treatise of the essentials of carpentry.

No apology is offered for making use of trigonometric solutions of plane right triangles as a basis for developing generalized roof framing principles in Chapter IV. There is absolutely nothing in the use of natural trigonometric functions to prevent their introduction early in the mathematical experience of a boy, except academic tradition. The author has made use of this mathematical tool with upper grammar grade boys with less effort upon their part in mastering the principles than was expended in mastering square root. The ease with which roof framing problems lend themselves to solution by the use of natural trigonometric functions and the readiness with which problems may be generalized thereby has emboldened the author to make use of it in a text as elementary as this. No previous knowledge of trigonometry is presupposed, the Appendix provides all the information required for the solution of any problem given herein.

Should a reader, because of lack of time or for any other cause, not care to consider more than roof framing of the square cornered building, he will find a complete treatise in Chapter III without reference to solutions other than by common arithmetic. Appendix IV offers a still more abbreviated approach to both square and octagonal roof framing.

The greatest good in studying the chapter on "Estimating" will come only when each student is provided with a set of plans and specifications completely drawn, as by a practicing architect. Plans and specifications, such as will serve the purpose, can be purchased at small cost from architectural companies, should local architects be unwilling to provide sets for the schools.

Also, there must be provided for each student, catalogs of lumber and millwork specifications and prices. These can be obtained from mail order lumber and millwork companies. As a rule, local lumber and millwork companies are glad to provide such data, but it must be in a form complete, and readily accessible to be of the greatest value.

Ira S. Griffith.

Columbia, Missouri, September, 1916.

CONTENTS

CHAPTER I. FOUNDATIONS 13 1. Laying out; 2. Grade line; 3. Excavation; 4. Foundations; footings; 5. Foundation materials; 6. Forms for concrete walls; 7. Waterproofing; 8. Basement frames. CHAPTER II. MAIN FRAME 27 9. Methods of framing superstructure; 10. Sills and girders; 11. Bridging; 12. Trimmers and headers; 13. Walls and partitions; joists and rough floors; 14. Openings in framework. CHAPTER III. ROOF FRAME: SQUARE CORNERED BUILDING 45 15. Roof framing; 16. Framing the common rafter; laying out the plumb cut; 17. Finding the length of a common rafter; 18. Laying off a common rafter seat cut and end cut. 19. Ridge piece; 20. Hip and valley rafter; 21. Framing hip and valley rafters; 22. Side or cheek cut of hip or valley rafter; 23. Determining length of hip or valley rafter; 24. Laying off and end cut of hip rafter; 25. Reduction of hip or valley length seat cut because of ridge piece; 26. Backing a hip rafter; 27. Valley rafters; 28. Framing jack rafters; plumb cut; side cut; 29. Lengths of jacks. CHAPTER IV. ROOF FRAME: ANY POLYGON 69 30. Tangents; miter cuts of plate; 31. Octagonal roofs; 32. Common rafter for plate of any number of sides; 33. Hip and valley rafters for octagon and other polygons; 34. Plumb cut of octagonal and other polygonal hips and valleys; 35. Side or cheek cuts of hip or valley rafters, any polygon; 36. Rafter lengths of octagonal and other polygonal hips and valleys; 37. Reductions in lengths for king-post; 38. Seat cut and end cut of octagonal and other polygonal hips and valleys; 39. Backing octagonal and other hips; 40. Framing octagonal and other polygonal jacks; 41. Side cut of octagonal and other polygonal jacks; 42. Lengths of octagonal and other polygonal jacks; 43. Framing by means of a protractor; 44. Translating framing problems from protractor to framing square and vice versa; 45. Framing an octagon bay; 46. Framing a roof of one pitch to another of different pitch; 47. Framing roof of uneven pitch; 48. Decks; chimney openings. CHAPTER V. EXTERIOR COVERING AND FINISH 95 49. Sheathing; 50. Scaffolding; 51. Cornice; 52. Raked mouldings; 53. Shingling; 54. Shingling hips and valleys; 55. Finishing exterior walls; 56. Setting window and door frames; 57. Siding. CHAPTER VI. INTERIOR FINISH 115 58. Lathing; grounds; 59. Interior walls; 60. Stair building; porch steps; 61. Risers and treads; 62. Porches; 63. Interior finish; 64. Setting door jambs; 65. Fitting window sash; 66. Placing door, window, and other trim; 67. Hanging doors; 68. Fitting a door; 69. Hinging a door; 70. Fitting locks; 71. Laying and scraping floors; 72. Door and window frames; 73. Woodwork in masonry structures. CHAPTER VII. ESTIMATING 142 74. Methods of estimating; 75. Table for estimating by cubic-foot unit; 76. Grading rules; 77. Estimating lumber quantities; 78. Estimating millwork quantities; 79. Example of form for bill of materials; 80. Estimating labor costs; 81. Estimating quantities of nails; 82. Example of form for carpentry costs; 83. Total building costs by percentages. APPENDIX 158 I. Natural trigonometric functions; formulæ deduced. Solution of right triangles, (brief) II. Table of natural functions (for degrees only). Interpolation III. Useful tables. Fractional equivalents for decimal values. Wood and machine screw sizes. Length and number of nails. Wire brads. Board measure table. Strength of materials. Stresses for structural timbers. Contents of brick walls. IV. Short cuts to roof framing. Directions for Griffith's Framing Tables V. Estimating Excavations. Masonry. Slate. Plaster. Painting. Bibliography of References Index

The house used as a model for many of the illustrations in this book.

CARPENTRY

CHAPTER I Foundations

Fig. 1. Transit.

1. Laying out Foundations.—In most communities it is customary for the carpenter to be present and to assist the mason in the laying out of the foundations. Where buildings are large and important, this work is done by an engineer with a steel tape and a surveyor's instrument, Fig. 1. This instrument is known as a builder's transit, and consists of a tripod upon which rests a small telescope with crossed hair wires within, by means of which the observer may fix the line of sight very accurately. A circular dial contains a magnetic needle which enables the fixed dial to be set with reference to the true north and south line of the observer. After the fixed dial has been adjusted, the telescope may be swung to the right or the left until the circular graduations indicate that it points in the direction wanted, after which stakes may be set. A level upon the telescope enables the observer to sight grades or levels; a helper carrying the leveling rod, Fig. 2.

Fig. 2 Leveling Rod

Fig. 3 shows a more common instrument. This is an architect's Y-level and differs from the other in that it is less complete. It has no attachment for measuring vertical angles. This is not serious, however, since the builder seldom needs such an attachment, the level being the most essential part. Y-levels are made both with and without compass attachments.

Fig. 3 Y-Level

Upon ordinary residence work a surveyor is employed to locate lot lines. Once these lines are located the builder is able to locate the building lines by measurement. Suppose it is desired to locate a building by means of the side lot line: (1) Measure from the side lot line, along the front and along the back lot lines, a distance equal to that which it is desired the house shall hold relative to the lot side line. Drive stakes here. (2) While sighting from one of these stakes to the other, have an assistant locate two other stakes in the line of sight, a distance apart sufficient to guarantee the placing of the cross-lines for the back and front of the house without restaking these, A-B, Fig. 4. The process of laying out lines for a house is almost identical with that used in laying out a rectangle on a drawing board. (3) Having located a line of indefinite length for one side of the house, a second line of indefinite length, preferably for the front of the building, may next be located. To do this, first locate a front corner stake upon the first line just located. This is done by measurement from the street line. Having located and driven in this stake, A , Fig. 4, drive a nail in the top of the stake to more accurately locate this corner.

Fig. 4. Batter Boards

If an instrument is available it will be located over this stake and the front line A-C, Fig. 4, located by laying it off at 90 degrees from the side line already located. If no instrument is available, the front line may be laid off at right angles to A-B by holding a framing square at their intersection. This angle should be verified by the 6-8-10 method. This consists in measuring from the intersection at A along one line a distance of 6 feet and sticking a pin in the line at that point; a pencil mark may be used when the cord is white. In a similar manner, measure off 8 feet along the other line and then measure the hypotenuse of the triangle so formed. It should measure 10 feet. If it does not, the front building line must be shifted until it does. (4) With these two lines located, the remaining two lines may be located by measurement from them, the nail of stake A giving the starting point. Before this is attempted, however, the batter boards should be placed. Batter boards are variously constructed. Those shown are common types. They should be placed free of the foundation proposed by at least 3 or 4 feet. (5) Test the squareness of the whole lay-out by measuring the diagonals A-D and B-C. If the building lay-out is square the diagonals should be equal. If they are not equal, shift the cords at C and D, retaining their parallelism, until the diagonals become equal. (6) Once the lay-out is correct, saw kerfs should be made in the batter boards where the cords are placed. These kerfs will permit the cords being removed and replaced without further measuring.

2. Grade Line.—A properly drawn set of plans will show both the present lay of the ground upon which the building is to be erected and the new grade line which is to be established after the building is completed. The most convenient method of determining old grade lines and of establishing new ones is by means of the transit, Fig. 1, or the Y-level, Figs. 3 and 5, with the rod, Fig. 2. Both instruments operate upon the same principle in grade work. The telescope is set level and sights taken thru it to the target upon the rod. The reading of the target's position upon the rod compared with the height of the telescope above the base, usually the street walk, determines the difference in grade of that particular placing of the target.

Fig. 5. Taking Sights with Y-Level

To locate levels for the masonry, (1) set the instrument at some convenient place and level the dial. (2) Having determined the height of the instrument above some predetermined base, such as the street walk, swing the telescope about and, making allowance for the difference in level as shown by the drawings, place successively stakes at each corner of the building with the required level marked thereon. As a rule, the mason has his own Y-level and uses it freely as the wall is constructed, especially where levels are to be maintained as the layers of material are placed.

Fig. 6. Leveling with Straight-edge

In a similar manner the earth grade about the building may be located, stakes being driven into the ground at frequent intervals and the amount of "fill" or reduction indicated thereon. Grade levels are established usually only after the builders are thru, except that the mason will have the grade indicated for him where the wall above the grade is to be differently finished from that below.

Where no surveyor's level is at hand, the mason or carpenter will secure the levels by means of a straight-edge of some 14 feet in length. A common level is placed upon this plank as shown in Fig. 6. By successive levels with stakes driven to indicate the successive levelings, a grade may be carried quite a distance without very great variations.

Fig. 7. Foundation Detail

3. Excavations.—Excavations should be made enough larger than the proposed foundation that the mason may have room to wield his trowel in pointing the outer joints, and for waterproofing. An extra foot of excavation upon each side will usually be required.

All foundations must be carried well below the frost line. Excavations should be made accordingly.

4. Foundations; Footings.—Because of the tendency of a building to settle unevenly, due to variations in the strength of the supporting ground or the unequal weight placed upon this ground, foundations must be constructed of some non-yielding material such as brick or stone, and of such thickness and so bonded that the weight of the building may be evenly distributed.

The thickness of wall will depend upon the weight to be supported and upon the character of the soil.

Unless rock or gravel is encountered, every foundation should have a footing, Fig. 7. The amount of footing used is usually twice the thickness of the foundation wall. In brick walls this footing draws into the wall by "stepped" courses of brick, each layer being narrower than the one just preceding. For ordinary residence work with ordinary soil conditions a 10- or 12-inch wall resting upon a footing 2 feet wide and 8 or 10 inches deep will suffice.